Bajel Projects reportedly wins INR 1,500 crore Gujarat transmission package

Bajel Projects reportedly wins INR 1,500 crore Gujarat transmission package
My preferences

Bajel Projects Secures ₹1,500 Crore EPC Order for Gujarat’s 765 kV Transmission Corridor

The project covers approximately 270 km of 765 kV double-circuit transmission lines between Halvad and Vadodara, along with substation works linked to renewable energy evacuation in Gujarat.

Bajel Projects Limited has secured multiple Letters of Award (LOAs) worth approximately ₹1,500 crore from Lakadia A Power Transmission Limited for engineering, procurement and construction (EPC) works on a major transmission infrastructure project in Gujarat.

According to the company’s regulatory disclosure dated October 26, 2026, the order value includes GST and represents the largest transmission order in Bajel Projects’ history. The company has classified it as an ultra-mega order under its internal order classification policy. Source: Bajel Projects’ regulatory disclosure

A High-Voltage Corridor Supporting Renewable Energy Evacuation

The reported project scope includes approximately 270 km of 765 kV double-circuit transmission lines connecting Halvad and Vadodara in Gujarat.

Additional EPC works are planned at the Halvad, Vadodara and South Olpad substations.

The infrastructure forms part of the Common Transmission System for Evacuation of Power from Lakadia Phase II, Jam Khambhaliya Phase II and Jamnagar Phase I.

The respective renewable energy evacuation capacities associated with these regions are:

  • Lakadia Phase II: 7.5 GW

  • Jam Khambhaliya Phase II: 5.5 GW

  • Jamnagar Phase I: 1 GW

Together, these projects represent a planned evacuation capacity of approximately 14 GW.

The Halvad–Vadodara transmission line and associated substation works form part of this wider transmission programme. The 14 GW figure represents the broader system capacity, not the capacity of the individual transmission line awarded to Bajel Projects.

Source: Energetica India

Bajel Projects’ Dual Role in EPC Delivery and Project Development

Lakadia A Power Transmission Limited is a special purpose vehicle (SPV) established for the development of the transmission project.

The SPV was transferred by PFC Consulting Limited to AnantGrid Projects One Private Limited (AGPOPL), following the successful completion of the tariff-based competitive bidding (TBCB) process in August 2026.

AGPOPL is jointly owned by Bajel Projects Limited, which holds a 26% stake, and the National Investment and Infrastructure Fund (NIIF), which holds the remaining 74%.

This ownership structure gives Bajel Projects an equity interest in the project development entity alongside its role as the EPC contractor.

The company’s participation therefore extends beyond construction and delivery to include an ownership stake in the project development structure.

However, the available disclosures do not provide detailed information on project-level risk allocation, financing arrangements or the commercial terms associated with Bajel’s equity participation.

Potential Opportunities for Transmission Contractors and Equipment Suppliers

The project could generate opportunities across several segments of the power transmission and infrastructure supply chain.

Potential areas of activity include:

  • High-voltage transmission line construction

  • Transmission towers and associated steel structures

  • Conductors, insulators and line hardware

  • Substation equipment and electrical systems

  • Civil construction and substation infrastructure

  • Installation, testing and commissioning services

The scale of the project highlights the continued importance of transmission infrastructure in connecting renewable energy generation zones with the wider electricity network.

However, the specific procurement packages, equipment specifications and supplier participation opportunities have not been disclosed in the available information.

Execution Timeline and Project Milestones

According to Bajel Projects’ regulatory disclosure, the project is scheduled for completion within 36 months from the date of issuance of the Purchase Order.

This provides an initial execution timeframe for contractors, equipment manufacturers and infrastructure suppliers tracking the project.

The detailed construction sequence, individual package boundaries and commissioning milestones have not been publicly specified in the information reviewed.

Further disclosures on these aspects will help establish when individual transmission and substation components are expected to enter construction, installation and commissioning stages.

A Significant Addition to Gujarat’s Transmission Infrastructure

Bajel Projects’ ₹1,500 crore order reflects the scale of investment being directed towards renewable energy evacuation and high-voltage transmission infrastructure in Gujarat.

The project forms part of a broader network development programme intended to support renewable energy integration from the Lakadia, Jam Khambhaliya and Jamnagar regions.

For transmission contractors, equipment manufacturers and infrastructure developers, the project represents a significant EPC opportunity. Its execution timeline, procurement requirements and progress will be important indicators of activity across Gujarat’s power transmission supply chain.

Source: Bajel Projects Limited’s regulatory disclosure dated October 26, 2026, and industry reports published by Energetica India and ET EnergyWorld.